Kırklareli Mobilization Buildings

The project, consisting of 11,187.30 m² of prefabricated and light steel structures, meets the accommodation, dining, healthcare, office, storage and social space needs on-site, providing employees with a comfortable and efficient living and working environment

Project Information

Category: Construction Site and Camp Buildings
Products: Prefabricated, Container, Light Steel Structures
Scope: 1,633 m² Kitchen and Dining Hall Building / 122.81 m² Clinic Building / 894.53 m² Workers' Lounge Building / 500 m² Engineer & Technical Staff Lounge / 181.96 m² Laundry Building / 1,103.00 m² 2-Storey Foreman & Technician Dormitory Building, 3,309.00 m² 2-Storey Engineer Dormitory Buildings / 781.00 m² 2-Storey Manager Dormitory Building / 6,860.00 m² 3-Storey Workers' Dormitory Buildings / 2,135.00 m² 2-Storey Office Building / 1,000.00 m² Hangar Building / 360.00 m² Warehouse Building
Duration: 150 Days
Location Kırklareli

Kırklareli Mobilization Buildings

The project, consisting of 11,187.30 m² of prefabricated and light steel structures, meets the accommodation, dining, healthcare, office, storage and social space needs on-site, providing employees with a comfortable and efficient living and working environment

The project we implemented in kırklareli was designed to meet the essential needs of the site, including accommodation, social facilities, dining services, healthcare, offices, storage and light steel structures, ensuring a comfortable and efficient living and working environment for employees.

A 1.633 m² kitchen and dining hall was built to meet employees meal requirements, designed with a large capacity to accommodate both kitchen operations and large-scale meal services. Additionally, a 122.81 m² clinic building was integrated into the project to ensure uninterrupted healthcare services on-site, equipped with the necessary medical facilities. 

For employee recreation and socialization, a 894.53 m² workers lounge and a 500.00 m² engineers and technical personnel lounge were constructed. These structures provide a modern and comfortable indoor environment, offering employees a space to relax and unwind. Additionally, a 181.96 m² laundry building was building was built to meet the hygiene needs of on-site personnel. 

The accommodation facilities include a two-story dormitory for foremen and technicians (1,103.00 m²), two-story dormitories for engineers (totaling 3,309.00 m²), a two-story dormitory for managers  (781.00 m²) and three-story dormitories for workers (totaling 6,860.00 m²). These buildings ensure safe and comfortable lodging for employees working on-site. 

To facilitate site management, a 2,135.00 m² two-story office building was constructed, providing modern workspaces to support efficient business operations. Additionally, a 1,000.00 m² non-insulated hangar and a 360.00 m² insulated storage building were included in the project to protect equipment and expand workspace capacity. 

All transportation and installation process were meticulously managed, within a detailed logistics plan, ensuring the safe delivery and assembly of dormitories, office, social areas and hangars. The fast installation advantage of prefabricated and light steel systems allowed for the rapid completion of essential living and working spaces on-site. This project aims to fully meet the needs of site personnel by providing high-quality buildings solutions, creating an efficient and comfortable working environment.